[ARCHIVED] 2021 Fall Graveling Schedule

Fall Gravelling Picture

Fall graveling is starting September 9th. See schedule below for work being done in your area.

  • East County Boundary to Hwy 2 – The majority of the graveling has been completed by County trucks over the summer and the remainder will be done when gravel crushing is complete.
  • Hwy 2 to Range Road 55 – Work being done by Hopkins Construction (Lacombe) Ltd. and will commence Monday, September 20th starting at Hwy 2 and working westward.
  • Range Road 55 to west County Boundary – Work being done by County trucks and will commence Wednesday, September 9th.

If you have any questions regarding fall graveling, contact Brian Anderson, Public Works Manager of Operations at 780-361-6244.

Facebook Twitter Email

Other News in County of Wetaskiwin News

Kids Can Catch 2025

Kids Can Catch

Posted on: June 26, 2025
July 2025 FS

Fireworks

Posted on: June 30, 2025
County Transfer Stations

TRANSFER STATIONS - CANADA DAY HOURS

Posted on: June 23, 2025
Babysitting

FCSS - Babysitting Course

Posted on: May 6, 2025
Home Alone

FCSS - Home Alone Course

Posted on: May 5, 2025
Program Guide News Flash

FCSS - Community Program Guide

Posted on: March 7, 2025
Assessment - Rotational Inspections

Assessment: Rotational Inspection Areas

Posted on: October 16, 2024