Project Description:
This project intends to provide road users with an all-weather dust free driving surface from the Highway 2 overpass at Township Road 470 to Highway 616. The project involves repairing any existing failed areas, widening the road to a width of 9.0m, stabilizing the subgrade with a portland cement and sealing the road surface with a double aggregate seal coat. Culverts through the centerline of the road will also be replaced during this project. Construction is expected to start on August 26th and crews will be on site for about 30-40 days. This does not include days in which crews are unable to work due to inclement weather.
Scope of Work:
- Remove and Dispose Culverts
- Supply and Install Small Diameter Culverts
- Subgrade Excavation
- Borrow Excavation
- Cement Stabilized Subgrade
- Aggregate Seal Coat
We understand construction can be inconvenient and may cause minor delays, but your patience and cooperation are crucial. Let's work together to maintain a safe construction site throughout the project. View the full Notice of Construction here. Progress updates will be posted on our website and Facebook page.